33 On the re contract such face sample panels were
only made after repeated assurances that
Westmin would pay for them.
34 As the findings of the inq will be of such
wide interest and sig to persons ranging
from tenants to insurance coy to the
parent H N in D it would seem to be
imp that all similar parts of the
structure to that which collapsed, both
on the remaining building and in sim
bldgs would be checked for adeq rod
reinforcement fixings of face panels, and
correct location of bearing panels during
erection.
35 Whatever the outcome of the inq it
might be advisable that the claims of
the Projects Manager made in his annual
address at Sundarana to the effect
that the SB had superceded the Archt
should not be allowed to go unchecked
and that in future the NBA in granting
certif and the Min in granting loan
Sanct should not authorise a system
without an indep arch or consulting
engineer being attached to the system
to ensure that the profit motive
may not be detrimental to safety
quality R&D and the fut of SB
as a whole.