I am very concerned about the lack of
real prog on the LG project. Alan tells me
that the network prog as such is still
not agreed and finalised for use, due to
some doubts raised by Cyril Sweett. This
means in effect that no controls can be
applied and the longer this situation persists
the more dif it will be to retrieve
the sit ultimately.
I feel that a top priority meeting is
req to agree with Rigby* that the major
stages date on the prog must stand so
that it can be used as a control at
least for the stages currently being
worked and that the details of the prog
applied to C. Sweet's billing are negotiated
separately without prejudicing current
work. At pres there is no effective
control over the critical items up to
the stage of billing.
Poro though I feel entirely as a
result of the above, decisions are not
being taken on both sides. I have
enq closely into this with Alan
and it does seem clear that the bulk
of it is due to architectural
shilly shallying in one form or another
due to the inherent reluctance to
make a final decision on any partic
point.
Unfort there appears to be a marked
tendency for the Archts on both sides
to get together to maintain the state
of indecision rather than reach
decisions; this is helped by the
so-called Co-ordinator, on Westminster
st side being an Archt somewhat out
of his depth anyway.
I feel that real prog is only
going to be made by morale power