Notes on Inquiry

20 H: "To be safe, you would use more steel."
H: "It is not just a question of extra steel, I would have to
radically redesign the whole block.
21 May: "We are going to build higher?" "Presumably."
May: "Tribunal has 2 months. You feel it needs
considering over a much longer period?"
H: "Not a question anyone can rush into."
22 May: "Chemical factories, electricity substations."
"Aldershot building collapse."
H had not read report on Aldershot.
Insitu concrete and stuff on site.
Mortar of 5,700 psi.
23 Lack of friction between strap and floor a weakening
element which he (RAH) had not considered.
Admitted "majority of bolts not tightened right down".
24 Hardboard packs.
25 "Straps on top of floor unit not in contact with concrete."
26 Shear and jdnts.
27 Shear and joints.
28 Cumming (for British Constructional Steelwok Association)
cross-questions RAH, shows photographs where vertical
member severed without collapse.
29 Defence of frame building?
30 RAH hedges again on "no collapse in a frame building"?
Eveleigh + RAH joints, "order of merit".
31 RAH: "In a month's time, in a different frame of mind,
I might put them in a different order." (Very fine
differences in joints)
32,33 Still on reinforcement.
34 Eveleigh asks if scaffolding (6 storeys high) can be put
up on site for examinations of fabric.
E: "I was told that T.W. (interrupted by G)
Griffiths: "Someone has to foot the bill, I suppose. The
answer is yes."
Goodfellow: "It's a questioh of time, 2 or 3 days, I
don't know what the purpose is. What about the Fire
Service, these extending ladders.
Jokes all round.
Griffiths : "Scaffolding, quite an expense."
(WHY ISN'T T.W.A. ASKED TO DO IT? Is G a timorous man?
He always seems to change the direction of the enquiry
when things get too near the bone. JL )