Statement Response from Ledbury Action Group and Ledbury Tenant & Residents Association

Residents had to run to the TRA hall in person to alert staff. Dave Rowson; Southwark’s Fire
Safety Manager apologised, but the residents are left with little faith in the current fire
safety arrangements.
6. The measures were not fully complied with as stated in (5)
11. Frequent reports from residents of miscommunication and bad attitude from some
Southwark staff based at the TRA hall led to the Ledbury Action Group introducing ‘Independent
Observers’ to accompany residents upon request, to seek information. The Ledbury Action Group
were told, however, by staff at the TRA hall that their poster regarding Independent Observers
would be removed as it was classed a ‘flytipping’ if they added it to the noticeboard. Such is just one
example of the attitude of some staff there. Residents have been left in tears on many occasions.
Residents have also expressed concern over the lack of privacy at the TRA hall where personal
information is being discussed and shared in a large open room amongst many other people. Cllr.
Cryan promised that she would address these matters, however, little has changed on the ground.
13. The letter from Southwark of 10th August has not been posted on the Ledbury Towers website.
This letter has caused much confusion amongst residents as it stated that Southwark would be
decanting in the coming weeks and months. The following letters directly contradict that and
residents are still no clearer on whether they will be required to move or not.
14. ARUP made an error. They stated at the meeting of 11th July that Ledbury were Type ‘B’ tower
blocks and they seemingly relied solely on the BRE report that stated inaccurately that the
Commercial Way blocks were built in 1971. If either Southwark or ARUP had spoken to residents on
the ground, they would have discovered that some residents have been living there since 1968. Are
the Council still confident in ARUP?
18. What are the new structural implications given that ARUP have now discovered that no
structural strengthening appears to have been carried out on the Ledbury towers as recommended
by legislation following the Ronan Point disaster inquiry?
All the previous assessments & works were done on the assumption that strengthening had been
done. The residents are calling for urgent interim reassessment of the building structure to be
undertaken immediately. Residents are hugely concerned that large holes are currently being drilled
through the floors for the new district heating system and electrical rising main before a new
appraisal has been carried out. The risks of ‘accidental damage’ such as impact, high winds (as
mentioned by Large Panel System expert Sam Webb) and fire are reportedly enough to cause
progressive collapse. Additionally the ARUP report of 30th August worryingly states that ‘this limited
assessment has identified connection details that would require strengthening in order to enhance
the margin of safety to where it needs to be for this type of building for future use, to bring within
required limits the extent of damage that would be caused in the event of accidental damage to the
structure.’ This would indicate that currently, the building is outside of the required limits. Are
Southwark confident that they are prioritising resident safety?