Meeting, TRA Hall, Ledbury Estate, Draft Minutes

4.07 Q: What are the cost implications, and could the costs increase during the build?
NP: Costing is for the council and Calford Seaden to consider.
MT: Calford Seaden has only just seen the report. Full costings will be prepared by the
end of November. The report going to council is going to ask us to look again at the
costings.
AB: We have made recommendations, we have done some investigations, but we can’t
ever get all of the answers out of the building beforehand.
MT: 5.3.4 on p34 of the report sets out the further work needed if the project goes
ahead.
4.08 Q: Critics of LPS systems refer to them being like a ‘house of cards’. The concern is that
if a flank panel is removed, will these steel beams do the job supporting? Will the
building remain safe and rigid?
AB: Yes. If that situation arises, it is ready for action, but [under normal circumstances]
the flank panel is still doing its job supporting the building.
4.09 Q: Does this work take into account the gas supply and oxygen cylinders?
AB: One of our assumptions is that gas will not be reinstated, but yes, it would be safe
for oxygen cylinders.
4.10 MT: You are recommending a new slab on top of the foundations – is that the
equivalent of underpinning?
AB: No – you would be going in on the ground floor, removing the ground floor slab
and pouring concrete in between the ground floor and the foundations 2.5m below
ground.
4.11 MT: One assumption was to remove the concrete wall between the kitchen and living
room, which is a non-load-bearing wall. Does that also include other non-load-bearing
walls such as between the bathroom and the hallway, etc?
AB:. We will come back to you on that.
4.12 A resident expressed concern that the replacement wall would not be strong enough
to hang shelves from, etc.
4.13 Q: Would there be soundproofing added between flats?
AB: No – the walls between flats are all load-bearing walls which would not be
removed. We were suggesting the wall between the kitchen and living room, and the
corridor and the bedrooms, for example.
4.14 KW: On p30 of your report it refers under work ‘starting from the top floor’, to
‘remove the outer leaves of the flank wall panels’. What would that mean in practice?
AB: See p27: Part of the outer wall would need to be removed to access the inner wall
to fix the steel plate.
4.15 Q: What is the approximate timescale?
JH: We would need to formulate an approximate programme.
MT: I would guess 15 months.
4.16 MT: Why would the outer leaves of the wall be replaced with a lighter skin?
AB: It’s less to do with trying to reduce the weight of the façade, but once you remove
those outer panels it is very difficult to put them back again. It is more thinking, would
you put them back, and if not, what would you put in their place? It wouldn’t be