STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS STOP PRESS
HERE ARE SOME QUOTES FROM OFFICIAL REPORTS AND PRESS CUTTINGS :
Hillingdon reports that the system had not been properly
worked out when it was being produced, and revisions of
detail were made from site to site.
Portsmouth find that when concrete was poured into the
moulds it could often displace reinforcement, insulation
and fixing bolts. They also found an "irregular" number
of ties joining the inner and outer panel leafs together.
"In-situ concrete..........is of UNACCEPTABLY
POOR QUALITY. - Hillingdon.
Consultant engineers in Salford find that Bison blocks
are not properly strengthened to prevent progressible
collapse if there is an explosion. - Remember Ronan
Point?
John and Christine Keely of Barking have mushrooms
growing in their Bison flat. "We pull them off but they
just keep growing." Many other tenants on the
Gascoigne estate have chest complaints.
Wilkes St. in Salford. One tenant comments that there
is more rain inside than outside. In another block a
pensioner says "we've had problems with running water
for 16 years".
Secretary of a Newcastle tenants group says "nearly
every baby in these flats has a chest complaint because
of the damp".
In Manchester, where Bison were on site from 1971-9
trying to cure the problems, Mrs Hood of Pendlegreen
Close reported "I was woken up by this banging and I
went into the lounge. There were sparks flying across
the room and between the ceiling and the floor. It was
like indoor lightening. Frightening? - I was terrified".
[caption: THE WEATHER WILL BE FINE AND DRY]
The dangerous mixture of electricity and water is
familiar. A recent experts report on Nottingham noted
"ceiling rose disconnected to allow water to flow through
freely".
The ARCHITECTS JOURNAL sums up 6 Hillingdon
technical reports: "Problems have arisen from almost
every stage of the building process: faulty manufacture
of components, bad assembly and poorly executed
repairs to components damaged in the first 2 stages."
Barnet says it will cost £26, 685 to repair their flats
and even then "there can be NO GUARANTEE that all
the technical difficulties will be entirely overcome."
A Newcastle survey finds 84% of tenants homes have
damp on a Bison estate.
RUGBY TO CONSIDER SUEING BISON.
Terry Dicks, leader of Hillingdon Council claims -
"The Department of the Environment FOUGHT TO KEEP
REPORTS ON SYSTEM BUILDINGS SECRET and were
very reluctant to organise an interchange of ideas".
APRIL 1978 - 3 directors of BRYANTS, responsible
for building about 100 Bison blocks in Birmingham,
were sentenced to a total of 12 years in prison for
BRIBERY & CORRUPTION. The judge talked of a
"MUNICIPAL GOMORRAH".
BISON
OR BULL?
A report on the Bison System.
Available now from N.A.B.T.
NATIONAL ASSOCIATION OF BISON TENANTS
If you wish to know more about Bison or N.A.B.T.
please contact us at the addresses below:
154 Evans Court,
Old Basford,
Nottingham.
Tel (0602) 701686
( ") 865959
12 Harold Ave,
Hayes,
Middlesex.
Tel 01 5619400