London Borough of Newham Housing Committee, Joint Report of Officers

LONDON BOROUGH OF NEWHAM
HOUSING COMMITTEE - 3RD FEBRUARY, 1986
JOINT REPORT OF OFFICERS
[Handwritten sketch of a face/profile near top right]
DECISION ITEM
JAMES SINCLAIR POINT, ROCHESTER AVENUE, E13
WILLIAM WHITE COURT, GREEN STREET, E13
1. Summary
[Handwritten: GEY]
This report updates previous reports on James Sinclair Point, examines
the financial implications and concludes on technical and management
grounds that the block can be retained and proposes a methodology for this
to happen.
2. Recommendations
1. A Local Housing Officer dealing purely with the problems of
James Sinclair Point, taking a [circled: generic] role [handwritten: disfinate] and being based in an
Office/Surgery within the block. He/she would also assume a
management role in respect of supervising Porters and Cleaners.
2. Extending the Porterage Service to include the completion of [circled: minor]
repairs.
3. Review Porterage scheme with a view to extending hours of duty.
[Handwritten in left margin: Sai
part]
4. Upgrade standard Front Entrance Doors to flats. Each floor.
5. Provide individual door entry systems to each floor. Door Entry phone.
6. Initiate a local lettings policy on a co-operative basis and with
direct involvement from tenants. Initially in the short term,
priority should be given to households within the block in housing
need and expressing a wish to remain within the block.
7. Improved lighting to the surround area.
8. Consider [circled: the] use of National Car Park facilities for tenants' use.
9. Following the pilot scheme for cutting off the shear walls, a report [handwritten: 7]
be prepared outlining a definitive way forward.
[Handwritten arrow pointing to item 10]
10. A sum of £75,000 be allocated for enhanced security works.
11. An inter-departmental working group be established to consider the
future of J.S.P. and William White Court and the surrounding [handwritten: 7]
municipal owned land.
-----
12. Members are asked to note the compensation eligibility of the
tenants of William White Court.
13. [handwritten: A] Within the report to be produced on the proposals for James
Sinclair Point [circled: the compensation implications must be provided.]
The above strategies are seen in the context of the fire problem being
overcome to such an extent that the tenants' confidence is regained and
their continual residence affords the same degree of fire safety to that
of any other Council tenant.
Background
Following Committee consideration of the Joint Report concerning James
Sinclair Point and William White Court on the 28th January 1985, several
initiatives were targeted for implementation which directly related to
management issues. These basically included:-
1. The stablishment of a Porterage Service which included improving
the cleaning provision to the block.
2. Improved liaison with the tenants notably via the Newham Tenants
Tower Block Campaign.
3. Improvements to general security.
Summary of the Present Situation
1. Porterage Service
Three Porters are currently in post operating between the hours of
8 a.m. and 8 p.m. daily, additionally, there is a Resident Porter also
appointed. The Porters are linked by radio to each other and to Newham
Security Services Central Control.
In real terms, there is at least one Porter active in the block between
these hours. Predominantly he/she will provide security to the Main
Entrance/Exit at the Rochester Avenue end of the block, monitoring
visitors arriving and leaving. They frequently patrol the many communal
walkways in the block and attempt to show a presence at the
Entrance/Exit at the Queens Road end of the block. Inevitably this does
limit their effectiveness in vetting visitors to the block leaving the
problem of illegal access remaining evident until a full establishment
or Porters are appointed and an effective door entry system is installed.
In terms of establishment, there are remaining vacancies for 1 Resident
Porter and 1 Door Porter, both of which have been re-advertised and it
is anticipated that full establishment will be achieved by 1st February
1986.
[HAND-DRAWN SKETCH of animal/horse figure]
-----
The Cleaning Posts have been frequently advertised over the past few
months, however, to date suitable applicants have yet to present them-
selves. It is hoped that the situation will again be resolved by
the 1st February 1986, following a further session of interviews.
Although under-established the effect of this initiative has met with
relative success, for example :-
- Substantial reduction in vandalism and graffiti within the block.
- Improved liaisonwith local Home Beat Officer.
- Entrance areas are appreciably cleaner.
- Large items of rubbish are disposed of quickly.
- Report of lift failure and other communal services are dealt with
more effectively.
- Immediate response to emergency situations affecting tenants.
- Porters are seen as 'good neighbour' rather than figures of
authority.
- Porters are providing more intimate knowledge of the blocks and
possible difficulties from a tenancy point of view and management's
point of view.
2. Liaison With Tenants
Newham's Tenants Tower Block Campaign have set up an Office within the
block which is staffed on a daily basis. From the Campaign, there has
been the formation of the James Sinclair Point Tenants' Action Committee
dealing with the specific problems of the block, which has resulted in
improved formal communications between tenants and Council Officers, who
meet on a regular basis.
Coupled with an improved liaison with the tenants, the Estate Officer
has established closer contact with Social Services and Newham Building
Services when dealing with the special problems of James Sinclair Point.
3. Improvements to the General Security
A scheme of work has been prepared to refurbish the vandalised door
entry system and to create a new entrance at the Rochester Avenue 'Main'
Entrance. The new access is intended to be a 'focal point' for the
block and provide a base for the Door Porters.
The communal doors to the block will be strengthened and coupled with
this strategy, the north end of the block will be used for exit purpose
only, and for tenants access who have a door entry key.
These improvements are seen as essential to compliment the achievements
to date of the Porterage system, which is seen as the basis of our
security initiatives.
-----
Problems Still To Be Overcome
Although improvements have been evident within the block, there are
still many areas of concern to be overcome. These problems include:-
(a) The high number of households with 'special difficulties' has
provided additional management problems. Although this trend has
been reversed in recent years, many of the tenancies set up in
James Sinclair Point owing to its general undesirability, have been
households who have not been able to exercise a major degree of
choice in their housing preference, e.g., Homeless Persons and
Eviction cases from existing Council tenancies. This has resulted
in a great deal of tenant dissatisfaction and general apathy,
resulting in a lack of community involvement.
To conclude, the image and reputation of the block needs to be
altered drastically before it will become desirable from a lettings
point of view. However, it is felt that the steps taken to date
have formed the basis for future improvements.
(b) Tenants still have a general fear of insecurity, e.g., threats of
burglary or assault within the block. Although, the Porterage system
will, and has, make effective improvements, as will the envisaged new
door entry systems proposals, there is still a strong feeling that
individual flat doors should be renewed and strengthened to incorporate
a higher level or security.
(c) The general dissatisfaction of the partial electric underfloor
heating system which heats the living room and hallways only.
(d) External noise levels from both the market and especially the
railway creates problems for persons residing at the north end of
the block.
(e) The complete lack of car parking facilities.
(f) The generally poor environment surround the block, access to the
block is dominated by the presence of Queens Market, whether it is
during the dirty, noisy and busy daytime hours or the even more
awesome 'deserted and threatening' evening and night-hours. At night
although the market itself is adequately illuminated, it is full of
potential hiding places for would-be attackers and the surrouding
streets are generally deserted and inadequately illuminated.
(g) The fear of fire spreading rapidly upwardly should an accident
occur.
-----
Technical Issues
In recent months a scheme has been initiated within the block to clean
up all the communal areas and proposals for the door entry system have
gone out to tender. These two initiatives will make a considerable
difference, but they are only a beginning if the block is to remain
as being capable of letting.
The main problems of James Sinclair Point remain in that the problem
of fire transmission has not been solved, as outlined in the January,
28th report of 1985, there are several alternatives and these are outlined
below:
(a) Permanent baffles and essential refurbishment.
(b) Temporary baffles only.
(c) Permanent baffles and desirable refurbishment.
and all three options may be revised by cutting off the shear walls.
It is therefore proposed that a pilot scheme of cutting back part of the
shear walls be initiated so that an evaluation of the impact of such an
approach can be made. It is proposed that Tenants, Newham Tower Block
Campaign and Members would be present at the trial and a proper assess-
ment of the noise levels be made. Once this has taken place all parties
will be able to make decisions in the full knowledge of the problems that
would be experienced.
The answers to the external problems are laid out above, but the problems
of security as mentioned in paragraph [illegible] remain, and this has been a
constant request from the J.S.P. Tenants Committee. It is therefore, proposed
that a sum of £75,000 should be identified for security works within the
block.
-----
REVISED COSTS - JAMES SINCLAIR POINT
Referring to the Committee Report, 28th January 1985, to Housing.
Costs are as follows to February 1986 prices.
OPTION A - Permanent Baffles & Essential Refurbishment
Removal of Peripheral Beams £ 755,000
Repairs to Spalling
Concrete, Proprietary and
Decorative Face to Existing
Concrete, Scaffolding
and prelims
Construction and Fitting of £1,100,000
Fire Baffles and Provision of
Cavity Wall Insulation
Contingencies £ 45,000
Window Repairs and £ 130,000
Association External
Redecorations
Draught-proofing £ 17,000
----------
£ 2,047,500
Fees : £ 165,000
----------
TOTAL : £ 2,212,500
-----
REVISED COSTS - JAMES SINCLAIR POINT
OPTION B - Temporary Baffles Only
Repair Spalling Concrete, Securely £ 445,000
Fix Peripheral Beams
Scaffolding and Prelims
Fix Temporary Baffle £ 770,000
Contingencies £ 60,000
----------
£1,275,000
Fees : £ 100,000
----------
TOTAL : £1,375,000
OPTION C - Permanent Baffles & Desirable Refurbishment
Removal of Peripheral Beams £ 755,000
Repair to Spalling Concrete
Proprietary and Decorative Face
to Existing Concrete, Scaffolding
and Prelims
Construction and Fixing of Permanent £1,100,000
Fire Baffles and Provision of
Cavity Wall Insulation
Contingencies £ 45,000
Desirable Refurbishment inc. ) £3,222,000
Contingencies (as Committee report 25.1.85 ) ----------
£5,122,000
Fees : £ 410,000
----------
TOTAL : £5,532,000
-----
REVISED COSTS - JAMES SINCLAIR POINT
All three Options may be revised by cutting off the shear walls to
reduce the risk of fire spread, rather than use baffles.
The advantages are as follows:-
1. The cost of concrete repair to the shear walls is as much
of the deteriorated concrete is removed with the cutting.
2. The buildings profile becomes that of a normal tower block.
The safety against fire spread is therefore no worse or better
than the other blocks in the borough. The use of baffles can
not model textured, it is therefore unknown if the degree of
protection is better or worse for certain.
3. Removing the shear walls reduces the boroughs mutual maintenance
composed to baffles.
The main disadvantage is that the noise and disruption in cutting off the
shear walls is much greater to tenants than fixing baffles.
A trial run to assess the noise etc., could be undertaken and to this
end, I have arranged for two specialist contractors to give me quotations.
Upon receipt, I shall send them to you for your consideration.
-----
REVISED COSTS - JAMES SINCLAIR POINT
OPTION A - With Shear Walls Cut-Off
Removal of Peripheral Beams £ 920,000
Cut Shear Walls to
Flush with Building Scaffolding
and Prelims
Concrete Repairs £ 200,000
Contingencies £ 40,000
Window Repairs and
Associated External Redecorations £ 130,000
Draught-proofing £ 17,500
----------
£1,307,500
Fees : £ 105,000
----------
TOTAL : £1,412,500
OPTION B - With Shear Walls Cut-Off
Removal of Peripheral Beams Cut £ 920,000
Shear Walls to Flush with Building
Scaffolding and Prelims
Concrete Repairs £ 200,000
Contingencies £ 30,000
----------
£1,150,000
Fees : £ 92,000
----------
TOTAL : £1,242,000
-----
REVISED COSTS - JAMES SINCLAIR POINT
OPTION C - With Shear Walls Cut-Off
Removal of Peripheral Beams Cut Shear £ 920,000
Walls to Flush with Building Scaffolding
and Prelims
Concrete Repairs £ 200,000
Contingencies £ 30,000
Desirable Refurbishment inc. £ 3,222,000
Contingencies (as Committee report 25.1.85) ----------
£ 4,372,000
Fees : £ 350,000
----------
TOTAL : £ 4,722,000
-----
WILLIAM WHITE COURT
Further to the Council decision of 20.11.84, the tenants of William
White Court are having to be rehoused permanently because of a major
repair problem. Accordingly, tenants are entitled to a sum equivalent
to a Homeloss Payment (if eligible) and a Disturbance Payment.
IMPLEMENTATION
The future of James Sinclair Point has been discussed for a considerable
period, the tenants have requested some answers as to the future.
It is therefore proposed that:-
1. Following the pilot scheme for cutting off the shear walls
a report be prepared outlining a definitive way forward.
2. A sum of £75,000 be allocated for enhanced security works.
3. An inter-departmental working group be established to consider
the future of J.S.P. and William White Court and the surrounding
municipal owned land.
CONCLUSIONS
In the interests of the tenants of James Sinclair Point, it is necessary
that a decision making path be entered onto.