BISON CHECKLIST
110 QUESTIONS
BISON TENANTS CHECKLIST-110 QUESTIONS FOR YOUR COUNCIL TO ANSWER
BEFORE THEY CAN SAY "WE'VE LOOKED AT BISON PROBLEMS"
INTRODUCTION
Many successful tenants campaigns force Councils to investigate
building faults on the estate. However, all too often these
investigations are inadequate and half hearted.They miss major
problems,they only cover certain areas,they fail to answer crucial
questions.
NABT and other tenants organisations therefore try to deal with this
problems by making demands similar to that in the Bison Charter.
"All Bison Councils should immedistely launch,if they have not done so
already,a major investigation into every known Bison fault which might
exist in the flats they won"
The problem then is,what is a thorough survey? What questions should
it ask?
Below is a checklist which we believe any thorough Council should
follow up and answer. The questions are based on present knowledge of
the Bison system but the whole list can be adapted,with very little
variations for other systems.
We hope organisations will use this checklist by discussing it
themselves and by pressing the Council to adopt it as the basis for
any investigation that they do.
This is the first draft and hopefully it can be improved,please let
NABT know of any comments or criticisms.
STRUCTURAL
PANEL JOINTS
1.Are all the panels aligned properly within the tolerance allowed?
2.Do the joints rely on rubber baffles?
3.If so -are any missing?
or have any slipped or not been properly fitted?
how many?
what condition are they in?
4.Have any joints been filled in with a mastic since they were built?
5.Was this replacing old mastic,or were they originally designed not
to have any filling (ie be open drained joints)?
6.What condition is the mastic? Is it cracked,missing or not sticking
to the concrete?
7.How often will it need replacing and maintaining?
PANEL TIES
8.Are there any sandwich panels on the estate?
9.Are these loadbearing or non-loadbearing?
10.Are the two leaves of each panel held together by ties?
11.How many ties should be in each panel?
12.What material are the ties made of and what were they meant to be
made of?
13.Have tests been carried out to see if all the ties are present or
if any have corroded in any way?
14.How many panels were tested?
PANEL CONNECTIONS
15.How were the wall panels meant to be fixed at floor level and to
the ceiling?
16.How were the spandrel panels ( the ones running across the front
and back of the building usually,in almost very case there would be
windows in them) meant to be fixed?
17.How were other panels eg balcony,gable panels etc meant to be
fixed?
18.Do these methods meet modern Building Regulation standards?
19.In what ways do they differ?
20.Have investigations been carried out to prove all these connections
were carried out to the correct specification?
21.What strengthening was carried out,if any, after Ronan Point?
22.What strength explosions could the buildings withstand?
23.Have any panels shown signs of bowing?
24.If so,by how much?
PANEL STRENGTHS AND DURABILITY
25.Are there any signs of cracking or rust staining on any panels?
26.What length,width and depth are these cracks or defects?
27 In what position are they?
28.Are they in loadbearing panels,columns or other elements?
29.What percentage of panels are affected by cracks?
30.What methods have been used to look at cracks?
31.Have tests been carried out for calcium chloride?
32.How many panels have been inspected or cores have been taken?
33.What were the results of the tests?
34.Were calcium chlorides found in the original panels,in subsequent
repairs or both?
35.Has this calcium chloride affected existing concrete?
36.Have any bits of concrete fallen off since the flats were built?
37.Approximately how many pieces of what size and from where?
38.Is there carbonation of the concrete?
39.What percentage of panels are affected?
40.Is all re-inforcement adequately covered?
41.Are there any signs of corroding re-inforcement and if so on what
scale?
42.What is the estimated life of:
wall panels?
floor panels?
balcony panels?
roof panels?
bridge supports?
43.Were the panels made to the right dimensions eg in length,width and
thickness?
44.What tolerances were set down in the original specifications and
were these tolerances met?
45.What size sample was tested?
DRYPACK
46.Is the drypack fully compacted?
47.What was the strength of the drypack meant to be?
48.What is the actual strength of existing drypack?
49.Is is missing in any places,if so specify exactly how much is
missing?
50.How many places have been inspected for missing or substandard
drypack?
51.What is the structural significance and significance for fire risk
due to present state of dry pack?
WATER PENETRATION
52.What percentage of flats suffer from water penetration?
53.Does water come in through any of the following:
roofs
windows
balconies?
walkways?
panel joints?
Gable ends
internal drains?
anywhere else?
54.Has water penetrated the electrical system?
CONDENSATION,HEATING,INSULATION AND VENTILATION.
Heating,ventilation and insulation must all be looked at together
since they are very much connected together. Especially when looking
at condensation.
55.What percentage of flats suffer from condensation?
56.What is the approximate area affected in each flat?
57.Specify the extent and location of black and green mould?
58.Are there any mechanical extract fans in kitchen and the bathroom
eg Ventaxias?
59.If so,do they all work or are some broken?
60.Are the bedrooms heated?
61.Is the building structure of high or low thermal capacity (eg plain
concrete slabs have high thermal capacity which means they warm up
slowly whilst low thermal capacity structures warm up quickly).
62.If the building is of high thermal capacity is the Council
subsidising the heating in order to make up for deficiencies in the
structure?
63.What temperatures were the flats designed for?
64.What would be the current cost to heat a 1/2/3/4 bedroom flat or
houses to BS5449 and NHBC Grade 1? (See note at end)
65. What would be the cost of insulation to bring the dwellings up to
BS5499 and NHBC Grade 1 whilst keeping the running costs within the
average heating costs as produced by the government's Energy
Efficiency Office?
66.How much does the Council predict fuel costs will rise in the next
20 years in real terms?What effect will this have on tenants and what
consequences could it have for the building?
67.What cold bridges exist and where?
68.Are flats next to the lift shaft insulated?
69.Was all the original insulation inserted and was it inserted to the
correct thickness?
70.Has insulation become saturated and ineffective in any way?
71.What tests or thermographic surveys have been done to test for the
efficiency of present heating system,to find out sources of heat loss
and cold spots?
72.Is there heating to all rooms in the flat?
73.Are there easy to use heating controls which tenants can understand
and easily use?
74.Does any of the heating rely on drift heat ie.heat drifting
upstairs or from a landing into a bedroom?
75.Is the system a blow air system which causes dust and/or ill
health?
76.Are the heating charges similar or higher to average heating
charges ?
77.How often has the whole system been maintained or thoroughly
overhauled?
ASBESTOS
78.How many flats have asbestos in them?
79.Have any common areas got asbestos?
80.Where is this located ,what type of asbestos is it and what form
does it take eg panels,lagging?
81.What procedures does the Council propose to follow to remove and
dispose of it in complete safety?
82.What arrangements would be made to temporaily rehouse and
compensate tenants?
83.What information will be given to them and what consultation will
take place?
COMMUNAL AREAS,SOCIAL FACILITIES AND THE ESTATE IN GENERAL
84.Do tenants feel safe and in a friendly atmosphere living in the
flats?.Does the layout affect the atmosphere eg derelict garages,dark
dangerous stairs etc?
85.Are the flats sought after by people on the waiting list?
86.Is there sufficient community space,open space and shops?
87.Does noise from one flat disturb other tenants?
88.What is the cause of this?
89.If so what would be necesary to increase noise insulation?
90.How does the density compare with other estates?
91.Are there any complaints about rubbish shutes or disposal?
92.Are there adequate caretakers?
93.Can children get safe access to good play equipment?
94.Have there been any suicides or attempted suicides on the estate?
95.Have there been any plagues of firebrats,silver fish or other
insects?
OTHER
96.What remedial works are planned?
97.Would the proposed remedial works be 100% guaranteed to cure all
present problems?
98.Or could they possibly cause new problems eg move the damp from one
place to another,cause interstitial condensation ?
99.Would the flats be popular even after they were done up?
100.What would the expected life of the estate be after remedial work?
101.What is the condition of the asphalt on the walkways? And on the
roof?
102.Would a pitched roof solve roof problems?
103.Does the present building meet current fire regulation standards?
104.If not,in what way does it fail to meet these standards?
105.What qualifictions have any of the experts who have ben called in
to look at the blocks?
106.What other work have they done and what do tenants think of this
work?
107.Have they any interest in being involved in the remedial work?
108.Why should they be chosen rather than people who have already
looked at Bison?
108.Will they guarantee their recommendations to be correct?
109.Were they or their firm involved in any way in defective housing
in the past?
110.Have the Council or any consultants or investigators contacted
other Councils for advice and read all available offical reports and
the Bison Factpack and Bison Bilbliography?
British Standard 5449 says living rooms should be at 21 degrees C and
bedrooms,kitchen and toilet at 18 degrees C.The National housebuilders
Council Grade 1 standard says living rooms should be 21 degrees
C,kitchen 18,bedrooms 16.
This checklist researched and compiled for National Association of
Bison Tenants by SCAT.