IMG_0953

Notes on Inquiry

ARCHIVE DOCUMENT
Not stated
29 July 1968

17 (continued)

Gang guaranteed minimum BONUS and then PLUS RATE.

What does that mean?

PLUS rate means erectors got 3d extra.

52 Then they had guaranteed minimum bonus of 2/6d which
brought them to 9/6d an hour - 9 to 5.30.

They were doing 47 hours, on a five-day week.

July 2nd, seventh floor completed.

July 30th fourteenth floor completed.

8 o'clock till 6.30 p.m.

They could get 4/6d an hour bonus (an incentive).

NOT PIECEWORK, an incentive bonus system.

TARGET HOURS for erecting a flat.

5 flats a floor. If 150 hours allowed for each flat
750 per floor.

If 500 hours booked they'd get 250 hours at 75% of their
rate, which was 5/5d.

53 Phipps - It was a generous target, easy for them to earn money.

Averaged at R.P. 7 flats a week.

7 to 9 would give them a maximum when any negotiation
donw with Union.

(Which union? TGWU? JL)