Notes on Inquiry

17 (continued)
(He could have gone in and made a scandal about subsidies,
turned his defeat into an attack, instead of moaning and
wailing like this. JL)
13 Goodfellow puts it over that Ministry will have to fork out more
in future. Then saying, "You follow?" 3 times.
Asks North whether he would expect redress against the
contractor for a design error committed by structural
consultants.
North replies No.
Goodfellow drives it home. - Where you employ consultants
you do not normally get a guarantee that every design they
produce will work; merely that they have used every reasonable
professional skill and care in preparing it?
(Is this really true?)
In this case, Mr. North -
and he outlines TW's generous contract.
Contractorheld responsible for all work designed by him.
So North has a guarantee due to Phillips being servant/s
of T.W.
14 G screaming for a testimonial for Phillips from this
pathetic reed of a man.
G exonerating his bosses.
MAY sharp with North.
15 Asked if he really took any substantial part in design
of this building?
N - No, sir, in the hands of Phillips.
May - Do not risk it, Mr. North. Take your time - is it
correct .. TWA engaged in design and supply basis and
Phillips their structural consultants .. ?
N, after wriggling, - Yes.
16 Twice North - I do not understand the wording - for the
remainder of the dwellings.
Then he remembers that TWA were going to build some low
sotrey housing. 'At the time we thought we could engage
TWA. They are in fact being built by traditional methods
under a separate contract now'. (Did TWA pull out? JL)