Notes on Inquiry

ARCHIVE DOCUMENT
Not stated
26 July 1968

47 W gave building 'consideration', but 'I am not a structural
engineer'. His main worry wind pressure.

Spent a FULL DAY at Morris Walk, quite impressed by standard
of workmanship, fitting together of units etc.

Unless you start off properly, tumbles can arise.

At M. Walk everything seen to fit to within 1/16" or
1/4".

48 In 20 years he'd been at W. Ham 3 buildings designed for
explosive risks.

Clark got his factories mixed up.

(In fact Clark did not pretend to be exact, referred to
buildings round here.)

These had anti-explosive walls, wooden, open - louvred
panels lightly fixed so that they would blow out in the
event of an explosion.

Lists what they manufacture.

NEWEY examines. W pushed for C rather than B (wind) because
all other tall blocks.

2 Silvertown 22 (up 2 years).

3 Beckton Road 15 (up 5 years),

had been so designed.

Silvertown (the design of a particular consulting engineer)
= composite, partly framed,
partly panels hung from frames,
walls pre-cast concrete.

Beckton Road - traditionally framed, reinforced concrete
frame with brick panels.

You have not had any trouble with them?
No.

48,49 W - Let us put it this way : I work in the Borough Engineer's
Office, I am employed by Borough Engineer, etc.

Is Newham a particularly windy area?

W - Very prone to strong winds. He'd very nearly been blown
off quite a number of tall buildings.

IMG_0934