BUNN I fail to see the relevance of this. We havein fact used
seven.
BARNES Is it true that industrialised systems are used much more
on the continent?
BUNN I presume it would be fair to say so - again it is a
question of fact which can be ascertained.
KEATING How many years have you been the GLC's rep on the British
Standard Code of Practice committee?
BUNN 5 or 6.
KEATING Are you in the committee responsible now for any revisions
of C of P III which deals with this type of construction?
BUNN No. You may not realise that CP III will not in future
deal with large panel construction.
KEATING Is there a code which deals with it now?
BUNN I suppose the answer is - no.
KEATING There is, in course of preparation, a new C of P?
BUNN Yes.
KEATING When was it begun?
BUNN Three or four years ago.
KEATING Was the view taken that there was no urgency for producing
a new code?
BUNN I am not quite sure of the intention of the question.
These codes are looked into every so often and brought
up to date. The method of design, the approach and so forth,
were all looked into and a new draft prepared.
KEATING A new draft has been in preparation, for 3 or 4 years.
Meanwhile CP III was looked on as sufficient?
BUNN It was not proposed to revise it in any way.
KEATING Sufficient?
BUNN (cross) [illegible]
As I have said I am not in the code for CP III.
KEATING If I may come back to the question. The view was taken
that there was no urgency?
BUNN That is so.
KEATING It was felt that there was no need to have any special
requirement for high buildings.
BUNN No special requirement was suggested, no.

End of document