TWA Bid / Resume

T.W.A. Bid / Resume
1) ELHA with two Housing Associations (L & Q and Samuel
Lewis) and 3 Developers (Laing, McAlpine and Countryside)
want to bid to Newham Council for the tower blocks site.
The bid they would put would be a "Community - led"
scheme rather than a "Developer led" one.
2) The community representation in the scheme would be
through the T.W.A Group, and various parts of the schemes
which are to be developed would be aimed at local people
i.e. a community education facility; workshops; a self
build scheme (if it is wanted) and a local Housing Co-op.
3) The development of the site of would be done by a
development partnership of Associations and Developers,
which has to be settled within the next couple of weeks;
i) A lead Associations would bid for the sites, and own
them.
(ii) The blocks would be demolished one by one, probably with
one of the lead Association demolishing the first one for
half million pounds, with the Developers putting up £2.5 -
3 million for the remaining blocks.
(iii)An agreement would be drawn up before any blocks were
demolished giving land to community groups which could be
held in a trust, for community uses.
(iv) As the sites get re-developed, Housing Associations (or
locally based co-operative if it is up and running) can
buy sites and adapt the schemes at detailed design stage
at an agreed valuation, to be built by Laing, Countryside
or McAlpine, as housing for rent or part purchase.
(v) 4) As the scheme progresses, the Developers and Housing
Associations will make contributions to the Community's
Trust (as agreed in the original agreement) to put
towards the cost of constructing community buildings,
although these contributions will probably not cover the
complete cost of the buildings, and funds will have to be
sought from elsewhere to complete the projects.
4) Typically, up to 75% of Housing Association rented homes
go to the Council for nominations.
At the end of the scheme; the local residents should have ended up with:-
(i) a couple of sites for workspaces and community
education centre, with a contribution to building
the buildings held by the Trust, and help from ELHA
to find funding to complete the schemes.
(ii) a housing co-op if it is wanted, which could aim to
own around 20 homes.
(iii)a self build scheme if it is wanted, which could
probably build 10-15 homes.
(iv) a say in the housing mix, and house designs (i.e
housing of a reasonable size).
(v) a say in the planning of the overall area, around
the redevelopment.
(vi) a involvement in the criteria for affordable rented
housing and low cost/shared ownership housing in the
area.
(vii)the certainty that the blocks will actually be
demolished quickly and that the housing is
built as soon as possible.
6) The overall timescale of the redevelopment is likely to
be 3/4 years.