Ledbury Towers Meeting - Questions, Answers and Actions

Ledbury Towers meeting 23/8/17 – questions, answers and actions
| Question | Answer | Action |
| :--- | :--- | :--- |
| | **Heating, hot water and cooking: summary** So far we have accessed 34 flats to fit immersion heaters to provide a (limited) hot water supply to residents. In most flats we have had to remove asbestos in the locations needed for the new cylinders, and the asbestos contractors have accessed 51 flats. We have the ability to do 20 a day subject to residents giving access so if this happens could complete in two weeks. This is dependent on residents providing access. We have teams of both asbestos and heating contractors on site ready to do their work. Please make an appointment with your Resident Services Officer so we can complete this work without delay. <br><br> We have instructed Keepmoat to source and supply the number of electric cookers required, but cannot install these until the electrical supply within and to the blocks has been upgraded. These will be ordered by next Wednesday 30th August and the first batch will arrive for fitting within 7 days and the rest will follow within 1-2 weeks at latest. <br><br> The blocks electrical supplies and local network do not have the capacity for the additional load of immersion heaters and electric cookers. Keepmoat are currently on site undertaking works to the blocks over the next two weeks, and will be finished by 6th September and we are also working with UKPN in order to upgrade their local supplies to the blocks. We will keep residents informed of any proposed power outages as a result of this work. These will be for a working day each block. <br><br> Longer term we need to provide you with a proper, permanent heating and hot water service. <br><br> We plan to install a district heating system to each of the four tower blocks. Initially this will mean that each block will have a temporary large boiler sited somewhere outside the block on the ground floor. Pipework from the boiler will be run internally up the blocks and connected to the existing radiator and hot water circuit within each flat. <br><br> To do this successfully, and perhaps more importantly, quickly, before the onset of colder weather, we will need access into each flat on approximately four occasions. We know you are keen to have this done as soon as possible and we are aiming to have this work completed by mid October, in time for when we can expect colder weather, so we cannot understate the need for you to please provide the access needed to help us meet this timescale. | |
| 1 | Are you saying we can’t turn the heating on until mid-October? We are cold. | This is the time we turn on the heating in most of our blocks, but we understand this is difficult for some people who would normally top up heat with electric or other | We note this concern, and will provide a timeline regarding whether electrical heaters can be used by |