Report to the Ledbury Resident Project Group - Tuesday 5th November 2019

Update from LBS

Number remaining and recent moves

1. 178 properties are now void

2. 0 further offers have been made and have been accepted

3. 194 offers have been refused

4. There are 21 leaseholders remaining and 3 others are still in negotiation to
sell their properties back to Southwark Council.

5. 4 Bromyard tenants are now residing in Sarnsfield House and Skenfrith
House.

6. 1 Bromyard resident leaseholder is now residing in temporary
accommodation.

7. 2 Bromyard non- resident leaseholders now have their tenant residing in
temporary accommodation in Sarnsfield House.

Fire Brigade Spot Checks

8. There has been one more spot check since the last meeting and Green
Watch had no action for us to take.

Monthly Leaks Report

9. The log that we are maintaining shows 6 leaks since February 2019 as
follows:

| Block | Issue |
| :--- | :--- |
| Bromyard House | • 1 report of a leak from main intake pipes – resolved 11.03.2019 |
| Sarnsfield House | • 1 report of a leak from toilet cistern – affecting ceiling in flat below 06.04.2019 |
| Skenfrith House | • 1 report of a leak in the communal area on the ground – repairs gained access to leaseholder property and problem resolved. 11.03.2019 <br> • 1 report of a leak affecting three properties below on 29.06.2019 – resolved 01.07.2019 <br> • 1 report of a leak affecting two properties below on 21.08.2019 – resolved 21.08.2019 <br> • 1 report of a leak affecting one property below on 13.10.2019 – leak under kitchen sink resolved 28.10.2019 |
| Peterchurch House | • 1 report of a leak from a corroded copper pipe in a void – resolved 12.08.2019 <br> • 1 report of a leak affecting one property below on |