TBUK4065

Issues Raised by the Ledbury RPG at Cabinet

ARCHIVE DOCUMENT
Not stated
29 October 2019
Start of document

Issues Raised by the Ledbury RPG at Cabinet on 29th
October 2019

1. How long it will take to come to a decision based on this new
information

Response from Southwark Council
The costings from Calford Seaden will be ready by the end of November
2019 and therefore the December 2019 Resident Project Group will have
this information. At that meeting we will be able to discuss a possible
timeline for resident engagement which strikes the right balance
between the time needed for full resident involvement without causing
a concern about undue delays in getting to a decision about the future
of residents’ homes.

Once the Ledbury RPG has this information, officers will be discussing
with residents at the RPG on how the consultation on the options will
proceed.

2. That the reopening of the option appraisal will only include the towers,
and the red line boundary will be unchanged from the one used in 2018.

Response from Southwark Council
The reopening of the options appraisal will only include the Towers and
the red line boundary will be unchanged from the one used in 2018.

3. A commitment that there will be at least as many Council homes at the
end of this process on the site of Ledbury Towers and the rented homes
will be Council Homes for Council Rent

Response from Southwark Council
There are currently 203 council owned homes in the Ledbury Towers
and it is our commitment that there will be at least 203 council rented
homes at the end of this process. All council rented homes will continue
to be at council rents on secure lifetime tenancies.

4. Likely costs for tenants and the rent, service charge levels in new homes
with new homes offered to right to return tenants at the same rent and
service charge as their Ledbury Towers homes.

TBUK4065
65 of 137