Ronan Point Dismantling Report

ARCHIVE DOCUMENT
16 May 1986

INTRODUCTION

The London Borough of Newham is an area approximately 4 miles square,
bounded in the South by the Thames and the Royal Docks, in the West by
the River Lea, in the North by Wanstead Flats and in the East by the
River Roding. It is essentially comprised of the old Boroughs of West
and East Ham.

The quality and quantity of housing has been a problem to the area
throughout this century but the problems were scarcely touched by the
Local Authority prior to 1945 (West Ham had built 2,000 dwellings prior
to this), and the second world war brought massive destruction. In West
Ham, 27% of the housing stock was destroyed.

Nationally, there had been virtually no house building between 1939 and
1947, 500,000 were either destroyed or made uninhabitable and 250,000
were seriously damaged. The decision to use the public sector,
particularly the Local Authorities, for the task of rebuilding housing
stock reflected the values of the time. The private sector building
industry had been run down during the war and there was a shortage of
materials with everything rationed. Government planners estimated that
5,000,000 houses would have to be built in the first 10 years of peace,
although the actual amount fell short, the totals were impressive.

In 1944 Churchill unveiled the Capital's EFM Programme (Emergency
Factory Made) for prefabs. In one day a prefabricated house made in an
aircraft factory was driven to the site, unloaded in two pieces and
built onto prepared foundations and connected to services. In 1945 £150
Million was set aside for their manufacture. The production of the
prefabs totalled 124,000 and stopped in 1948; they were to leave a
powerful vision of the success of prefabrication in the minds of some
politicians.

Why High-Rise?

A major force for change was the question of density. More dwellings
had to be put back than were removed and in addition there was a demand
for increased service space, car spaces and play provision. There was
also the feeling that Britain was a crowded island, the population was
expanding and wartime experiences had emphasised the importance of
adequate agricultural land. Accordingly in areas of high land costs
Local Authorities could qualify for special grants to off-set the higher
construction costs of high rise. The Housing Subsidies Act 1956
positively encouraged high-rise building with subsidies ranging from £10
per annum for dwellings other than flats, through £50 per flat for flats
in 6-storey blocks rising by £1.15s. per flat for each storey in excess
of 6.

Why System Built?

One of the most important factors limiting the expansion of a housing
programme in many areas was the shortage of labour, particularly
tradesmen experienced in the traditional building skills. There was
also an increasing demand for new hospitals, roads, schools, offices and
factories, additionally competing for labour.

Industrialised building it was thought dispensed with the need for many
of these skilled trades and in the late 50s the expected expansion of
the economy led to the Government fearing an even greater shortage of
building labour and hence a possible reduction in its house building
programme which was aimed at 500,000 units per year by 1970.

In 1964 the National Building Agency was set up to advise Local
Authorities on the use of Industrialised Building Systems to solve its
housing problem and meet the Government's targets. By 1967 42% of all
dwellings built by Local Authorities and New Town Corporations were in
industrialised techniques.

By 1967 the expected shortage of labour and materials had not come
about, problems had been experienced in many areas with these design and
built packages and there was already a trend back towards traditional
building. The 1967 Housing Act cut the subsidy on dwellings over
6-storeys and the collapse of Ronan Point in 1968 effectively dealt the
death blow to tower blocks.

TWA SYSTEM BUILDING

The nine TWA blocks are of particular interest due to the collapse of
Ronan Point in 1968.

The nine TWA blocks form an estate in Canning Town and were built in the
late sixties. The blocks are constructed in large
panels of precast concrete jointed on site. The blocks were built by
Taylor Woodrow Anglian using the Larsen Nielsen System.

THE COLLAPSE OF RONAN POINT

On May 16th, 1968 some three weeks after Ronan Point was completed, an
explosion occurred in Flat 90 on the 18th floor which caused the
progressive collapse of the South East corner.

The cause of the explosion is believed to have been from a gas leak in
the kitchen although there is still some local doubt on this matter.

The explosion was sufficient to lift the ceiling panel of the flat and
this broke the insitu joint. There was then nothing to hold the flank
wall panel at the top and the pressure caused the flank wall to behave
as if it has a hinge at the bottom joint. The wall then fell out pushed
by the explosion. When this happened the 19, 20, 21 and 22 floors above
had no support. These floor slabs which were designed as simply
supported beams, then cantilevered from the kitchen wall and lacking top
steel snapped. The debris from the top floor flats then fell onto the
18th floor which collapsed under the load, setting up the progressive
collapse under gravity of the south east corner, right down to the
concrete podium.

DEVELOPMENT OF THE TALL BLOCK INSPECTION PROGRAMME

In the early 1980's it was becoming apparent that our inspection
techniques were not adequate to identify all the faults on a building.
Increased work was often identified once the building was scaffolded and
this led to urgent needs for increased expenditure on contracts after
they had been let. This then had a considerable knock on effect on the
individual contract programmes and the expenditure available for other
schemes in the Authority's Capital Programme.

In 1982 it was decided that the brief for the inspection cycle should be
enhanced so that all tower blocks were inspected at touch distance by
inspectors working from suspended cradles. Internal resources were
limited at this time so the programme was split between two consultants.
Building Design Partnership and Bullen and Partners, with a decision to
recruit and train in-house staff to gradually take over the role in
future years.

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

[illegible]

DISMANTLING OF RONAN POINT

Decision to dismantle

Following the investigations at Ronan Point, costings for refurbishment
of the block were formulated.

(i) Essential Works: Structural strengthening to 5 lb\sq.in., fire
stopping and necessary works to the fabric and services were
estimated at £3,144,000 or £28,600 per flat. Strengthening to 5
lb\sq.in. was included despite the fact the block has no piped gas
due to the problems of policing out LPG from flats.

(ii) Desirable Works: Additional works necessary to bring the dwellings
up to reasonable modern standards and be able to assist in the
effective management of the block were estimated at £5,724,000 or
£52,000 per flat.

The above costs being as at October 1984.

Since even the minimum option was unlikely to obtain DOE PC2 approval,
and even if it did officers could not recommend utilising public funds
on this scale merely to bring unsatisfactory housing back into use,
demolition was clearly the correct course of action. Another factor was
also the social considerations as even if the Council were prepared to
make the investment necessary to rehabilitate these blocks, bearing in
mind the past history it was considered that there was little prospect
of homes being provided which would meet with tenant satisfaction. The
Council have also agreed to the demolition of the other nine T.W.A.
Tower Blocks.

Full Dismantle

This proposed that the block be dismantled in a reverse building manner.
The joints would be split and the panels removed as whole and lowered to
the ground for disposal.

This method was adopted for the Contract documents for the following
reasons:-

i) Allowed the asbestos faced sheets to be easily dealt with

ii) Allowed panels to be provided to the Building Research
Establishment with the minimum disruption

iii) The method only required one property No. 87 Butchers Road to be
evacuated and would create the least disturbance, noise and dust to
local residents

iv) It was considered to be the most economic method in the
circumstances.

THE FUTURE FOR NEWHAM'S HIGH RISE BUILDING STOCK

There is a high level of dissatisfaction from many tenants living in
high rise blocks. The utopian solution if sufficient resources were
available would be for the Authority to provide sufficient low rise
stock of suitable quality to enable the demolition of the blocks. The
available resource level is however well below the level required to
adequately maintain them, let alone replace them. In addition certain
of the blocks do work, the right combination of maintenance levels,
security, tenant mix and management strategy allows them to make a
significant contribution to the Authority's stock of satisfactory
housing. However, currently only one of the stock of 22 storey blocks
can be said to be satisfactory and that is because considerable
financial and managerial resources have been expended in converting it
to sheltered housing. Consequently there is additional pressure to
limit the life span of the remaining 22 storey blocks. Essentially the
majority of the stock will have to perform the role of providing at
least adequate housing for some way into the future.

THE FUTURE FOR NEWHAM'S HIGH RISE BUILDING STOCK

There is a high level of dissatisfaction from many tenants living in high rise blocks. The utopian solution if sufficient resources were available would be for the Authority to provide suitable alternative stock to enable the demolition of the blocks. The available resources however will fall below the level required to adequately maintain them, let alone replace them. In addition certain of the blocks do work, the right combination of maintenance levels, security, tenant mix and management strategy allows them to make a significant contribution to the Authority's stock of satisfactory housing. However, currently one of the stock of 22 storey blocks can be said to be satisfactory and that is because considerable financial and management resources have been expended in converting it to sheltered housing. Consequently there is additional pressure to limit the life span of the remaining 22 storey blocks. Essentially the majority of the stock will have to perform the role of providing least adequate housing for some way into the future.

George R. Iley,
C.Eng., F.I.C.E., F.I.H.T.
Director of Engineering and Surveying,
25 Nelson Street,
East Ham,
London.