Newham Tower Block Tenants Campaign Emergency Meeting Notice

ARCHIVE DOCUMENT
Start of document

I am writing to you regarding the emergency meeting of the Housing Committee on
Saturday, August 4th. The meeting is being held, I believe, to discuss the future
of the eight Taylor Woodrow Anglian blocks on the Freemasons Estate, following
the disastrous results of the fire test on 18th July.

As you are probably aware, the operation was organised to test a fire stopping
detail which if successful was to be installed as a temporary measure to fill
the gaps between the floor slabs and the wall panels. The experiment was carried
out in ideal circumstances with the Fire Brigade on site and steel girders installed
to prevent movement of the load bearing wall.

However, the fire which was expected to burn for around 20 minutes had to be
douced after only 12 minutes as the building became in danger of progressive
collapse due to severe deflection and cracking of the floor slab. If the building
had been left to burn, it is likely that there would have been a repeat of the
1968 collapse.

There is now a high level of both anxiety and anger among the tenants. N.T.B.T.C.
held a public meeting on Monday, 23rd July and 500 people attended along with
media representatives. The tenants expressed little faith in the engineers for
several reasons. For instance:
1) the glass through which the cameraman was videoing the fire actually melted
which indicates that the flat got much hotter than the engineers expected;
2) structural damage occurred after only 12 minutes. This was totally contrary
to the engineers expectations so how seriously are tenants supposed to take the
results of the other structural tests;
3) tenants believe that the buckling of the load bearing wall was also contrary
to engineers expectations.

Furthermore, tenants are very worried that, at the fire test, the fire brigade
were on hand to put out the fire immediately it became dangerous - in fact after
just 12 minutes. In the event of a real fire it is improbable that the fire brigade
could reach the scene and extinguish the fire within so short a time. Presumably,
therefore, the block would be in serious risk of collapse before the fire brigade
brought it under control.
Council members must not underestimate the feelings amongst the tenants of Freemasons
Road. 500 tenants do not attend meetings called at short notice unless the whole
community is deeply worried. Many were deeply worried before the fire test but
now real fear is deep and universal.

N.T.B.T.C. and the tenants of Freemasons Estate are thus demanding that the members
of the housing committee agree to decant the eight blocks, using the housing
department's own time scale (incorporated into their 2nd contingency plan ), of
6 months. They feel that 6 months is a reasonable period of time taking into
(continued)